Airfield pavement rehabilitation programme

Auckland Airport’s ongoing pavement replacement programme for runway aprons and taxiways continues. In the short term, the lower traffic environment provides opportunities to progress this programme with minimum operational impact, the following areas are planned for upcoming pavement works:


2021

April - July


Taxiway K and D8

July - September


Taxiway B5, B6 (south) and Taxiway A (between A5 & A6) –

September - October

Taxiway B4

October - December

Taxiway B5, B6 (north)

2022

February - April 2022


Taxiway B2

April 2022


Taxiway B (between B5 & B6)
Links to detailed Method of Work Plans for these projects are available below:

Taxiway K & D8

Download PDF

Taxiway B5 & B6 (south)

Download PDF

Taxiway B4

Coming soon

Taxiway B5 & B6 (North)

Coming soon

Taxiway B2

Coming soon